Progress Report
The last of the footings for the sanctuary as well as the upper elevator landing walls have been poured, along with the base for the tower. The lobby slab will be poured next followed by the lower sanctuary slab. Seven out of twenty-one feet of our block retaining wall is also finished! Below grade roughins for electrical, data, and plumbing in the sanctuary are coming along nicely.