Progress Report
The excavation company made significant progress on the construction site, finishing the building pad for the children's wing and nearly completing the admin wing pad. They also focused on grading the green space areas on the north, east, and west sides, while tackling rock excavation near the breezeway in the admin wing. They have also worked on grading for the west retaining wall. Rebar for the children's wing has been delievered and the foundation digging will begin shortly!