Progress Report

Construction progress by location:

  1. Children's Wing
    • Sheathing & conduit work ongoing

    • Sheathing joints sealed

  2. Admin Wing

    • Framing & sheathing work ongoing

    • Plumbing and ductwork

    • Sheathing joints sealed

  3. Lobby

    • Framing work began

  4. Sanctuary

    • Prepped for roof decking

    • Welding of tower steel continued

    • Elevator shaft steel set


10-Year Anniversary & Topping Out Ceremony

March 16 was a special day for C3! We spent the morning looking back at the last decade of God's blessings and faithfulness. Then in the afternoon, we looked forward to what He is doing in and through the life of our church. All praise, glory, and honor to Him! Take a look...

Progress Report

The winter weather stopped almost all site activities for two days but the teams were able to get much accomplished the rest of the week! A good chunk of the sanctuary lobby steel has been put up. Once the bigger pieces are finished they'll move the crane down the hill to be able to start the main sanctuary steel. A lot of the interior and exterior framing at the children's wing is now done and detail work like the openings for the changing tables, recessed trash receptacles, fire extinguisher cabinets, box headers, etc is being worked on. Good progress on overhead conduits and boxes for home run circuits for the receptacles and lights is being made and the crew has started mounting wall boxes. More ductwork is up and the plumbing in the walls at the children's wing has been started.

Progress Report

The upper and lower sanctuary slabs are now poured, so that means all major building slab pours are complete! The stepped area of the sanctuary will be poured after the steel is set due to how everything ties together. Metal stud framing at the children's wing is finished and the parapet walls around the roof as well as interior wall framing for this wing will begin shortly. The retaining wall is now at 15 feet and we should have power on the site within the next couple of weeks!

We Went Vertical!

Michael and Josh show us the latest updates to our building and share what's coming up next!