Merry Christmas!
We are excited to be in progress with our building and as a community resting in the finished work of Jesus! Looking foward to what this spot will look like in December 2025. To God be the glory!
We are excited to be in progress with our building and as a community resting in the finished work of Jesus! Looking foward to what this spot will look like in December 2025. To God be the glory!
Kinco hit a big milestone this week getting both the children's wing and admin wing slabs poured! The crew also made great progress digging the sanctuary footings. The primary power, data, and sign power conduits are nearly complete across the site along with the storm drain piping. We also received the roof steel bar joists and decking for the children's and admin wings.
C3 Staff got to take their first tour of the property since groundbreaking! We are excited for an oppportunity in the spring for our church family to get to come out and do the same!
The excavation company has worked on grading around the west side of the site, including the west retaining wall and the sanctuary building pad, along with rock excavation. The concrete contractor prepped and poured the foundation walls for the admin wing and worked on the footings for the same area. Density testing was conducted on areas where fill had been placed, as well as at the bottom of the children’s wing footing excavations. Data and primary power conduits for the admin wing have been started along with digging for the Entergy primary power pull box. Inspection for the below-grade sewer rough-in at the children’s wing passed and excavation for the below-grade sewer lines at the admin wing has also begun.
The excavation company has finished the admin wing building pad. They continue grading along the south side of the building, as well as the parking lot and west side green space areas. The children's wing perimeter footing has been dug, and work is being done to tie the rebar for the foundation.